PM World Journal Vol. IV, Issue V – May 2015 www.pmworldjournal.net Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Featured Paper Yosep Asro Wain Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design By Yosep Asro Wain, CCP Abstract Work breakdown structure (WBS) is a hierarchical decomposition of the scope of work, with the lowest element is a word package, which can be scheduled, estimated, monitored and controlled. WBS is important matter in planning a project. There are many work breakdown structures i.e. product based work breakdown structure (PBS), activity based work breakdown structure (ABS), zone based work breakdown structure (ZBS), functional based work breakdown structure (FBS), etc. To mix these structures, it is developed 3-dimension of work breakdown structure (3DWBS), which could be represented by one cube, with three sides. In a project, engineering design is activities to produce deliverables in the form of engineering documents, which will be used as the basis for project implementation. Engineering design activities are carried out throughout phase of the project. So that, engineering design has product dimension that contains deliverables, and activity dimension which is phase of the project. This paper describes implementation of 3-D WBS in engineering design. The 3D-WBS of engineering design using deliverables as PBS side, project phase as ABS side and project area as ZBS side. Keywords: Work Breakdown Structure (WBS), 3-Dimension Work Breakdown Structure (3-D WBS), Engineering Design, Project Phase. 1. Introduction Project objectives and the scope of work form a basis of a project. Project objectives, that address technical, schedule and cost aspects of the project, are the key parameters that must be achieved for the project to be considered successful. While scope of work is the written definition of the project’s technical parameter, that can be included technical specification, statement of work, project plan, and combinations of document. An effective project management system uses project objectives and scope of work as the foundation of the planning process. Conversion of the project objectives and scope of work into logical and manageable units of work constitutes the work definition process. The work definition process consists of 3 steps, namely: 1) creation of technical statement of work; 2) developing of work breakdown structure (WBS); and 3) preparation of WBS dictionary. © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 1 of 11 PM World Journal Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Vol. IV, Issue V – May 2015 www.pmworldjournal.net Featured Paper Yosep Asro Wain Technical statement of work includes technical objectives of the project, specification and major work product. WBS logically displays subdivisions of the complete project into smaller, more manageable, pieces of work. WBS dictionary serves as statement of the project scope for each WBS element (Humphreys, G.C., 2011). Project Objectives & Scope of Works Technical Statement of Works Work Breakdown Structure (WBS) WBS Dictionary Figure 1: Work Definition Process WBS is important matter in the planning, hence development of WBS for an activity is necessity. An important activity in a project, especially project in the process industries is the engineering design. In engineering design, alternative plant configurations are defined and screened. Further, selected configuration is designed in process and non-process aspects as the basis for implementation or construction. Engineering design will produce engineering document as its deliverables. This paper will address WBS of engineering design for the process industries project. Besides deliverables, engineering design also has other dimensions, that are phase and area of the project, therefore three-dimensions of WBS will be applied. 2. Work Breakdown Structure Work breakdown structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables (PMI, 2013). The scope of work should decompose progressively until manageable units of work, that are work packages are defined. A work package consists of group of activities which will be scheduled, estimated, monitored and controlled. © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 2 of 11 PM World Journal Vol. IV, Issue V – May 2015 www.pmworldjournal.net Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Featured Paper Yosep Asro Wain Figure 2: Product Oriented WBS Use product-oriented WBS as best practice, where WBS elements are decomposed from scope of work based on products or deliverables. Figure 2 shows example of product-oriented WBS (US GAO, 2009). As shown in Figure 2, WBS could be presented in tree structure, matrix or hierarchical structure. Sometimes, WBS is formed based on phase of the project (PMI, 2013), as shown in Figure 3. Figure 3: Phase-Based WBS © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 3 of 11 PM World Journal Vol. IV, Issue V – May 2015 www.pmworldjournal.net 3. Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Featured Paper Yosep Asro Wain 3-Dimensional Work Breakdown Structure Beside product and phase based work breakdown structure as mentioned above, there are many breakdown structures have been used. These structures include: • GBS (geographical based work breakdown structure), • SBS (systems based work breakdown structure), • FBS (functional based work breakdown structure), • RBS (resources or risk based work breakdown structure), • CWBS (contract based work breakdown structure), To mix these structures, it was developed 3-dimensional of work breakdown structure (3D-WBS). 3D-WBS has three dimensions, so that it could be represented by one cube, with PBS, ABS and ZBS as its sides, as shown below (Moine J-Y, 2013). Figure 4: 3D-WBS The PBS is constructed by systems, sub systems, product and sub product. The PBS answers the question “What?” The ABS, answers the question “How?” is constructed by phases, macro-activities, activities and sub activities. The ZBS is physic-functional, that divided by area or section. The ZBS can be a topographic view of the construction site of a project, or can be also viewed as functional zones, like for design phase and commissioning phase. The ZBS answers the question “Where?” The “3D little cubes” inside the WBS cube is the task or work package of the project. So that, a work package in 3D-WBS has product, activity and zone dimensions. The following is WBS matrix for 3D-WBS, in simple form (Moine J-Y, 2013). © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 4 of 11 PM World Journal Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Vol. IV, Issue V – May 2015 www.pmworldjournal.net Featured Paper Yosep Asro Wain Figure 5: 3-D WBS Matrix Engineering Design 4. Engineering is the application of science to problem solving, while design is the creative expression of knowledge. Hence, engineering design is creative process which applies science to solve a problem. Design, in general point of view, is composed of the following steps (Mody D and Strong DS): • Determine the problem and its constraints. • Generate potential solutions. • Develop sufficient detail that solutions can be compared and eliminated. • Implement the preferred solution. In chemical and process industry, design includes product and process design. In many ways, both are similar, one thing different is process design more emphasis on manufacture of known product, while product design more about invention of new products. This paper will touch process design, instead of product design. In “text book”, process design is commonly broken down into the following stages: • Problem Definition © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 5 of 11 PM World Journal Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Vol. IV, Issue V – May 2015 www.pmworldjournal.net Featured Paper Yosep Asro Wain • Process Synthesis, where multiple solutions are generated and discarded to produce a small number of favorable solutions that are taken to more detail. • Process Design, where one or two most favored solutions are developed in enough detail that reasonable financial analysis can be performed, safety and environmental issues can be identified and their risk understood. • Process Analysis, where optimization of the conditions or equipment will be performed. However, in practice, steps of process design are intrinsically linked to the phases of projects as follow: • Conceptual Study • Feasibility Study • Basic Engineering Design • Front End Engineering Design • Detailed Engineering Design (DED) Since in the process design, science and technology of the process are applied, so that process design is also referred as process engineering design or just engineering design. Figure 6 shows engineering design phase. Conceptual Study (CS) Feasibility Study (FS) Basic Engineering Design (BED) Front End Engineering Design (FEED) Detail Engineering Design (DED) Figure 6: Engineering Design Phase Conceptual Study (CS): A study to define the potential of a project, and determine if there is sufficient opportunity to justify the investment required for further study. In the process industries case, conceptual study is to develop alternative configurations of the plant by screening them from possible configurations. The result of conceptual study is shortlisted option of plant configuration that presented in form of block flow diagram. Feasibility Study (FS): A study to select the preferred configuration of the plant from the shortlisted defined from conceptual design. Further, the selected configuration will be defined more detail in process, utility, HSE, cost and economical aspect. The objective of this study is to provide information for decision on whether the project is feasible or not. © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 6 of 11 PM World Journal Vol. IV, Issue V – May 2015 www.pmworldjournal.net Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Featured Paper Yosep Asro Wain Basic Engineering Design (BED): In this phase, engineering design activities for selected feasible configuration will be started, including process and non-process design. It will be established the specific set of process operating conditions and equipment necessary to achieve the level of reliability, efficiency, and safety required. Front End Engineering Design (FEED): A continuation of BED, where some of engineering documents to be completed, i.e. equipment data sheets and engineering drawing. All engineering documents needed by EPC contractor to conduct detailed engineering design should be established. Detail Engineering Design (DED): For the purpose of procurement and construction of the project, EPC Contractor will conduct detail engineering design. This activity includes completing of the equipment data sheet for procurement and engineering drawing for construction. It should be noted that in practice, among the phaces may overlap, so that the number of phase may be less than five. For instance, conceptual study and feasibility study sometimes are combined into conceptual study or just feasibility study. Likewise, BED and FEED are merged into BED or FEED. In general, engineering documents produced during engineering design are block flow diagram, process flow diagram (PFD), piping & instrumentation diagrams (P&ID), plot plant, engineering calculation and drawing. These documents are developed in the early phases and progressively refined in subsequent phases. The following table contains deliverables of engineering design by phase of the projects (AACE International). Table 1: Deliverables of Engineering Design by Project Phase Deliverables General Project Data: • Project Scope Description • Plant Production/Facility Capacity • Plant Location • Soil and Hydrology • Integrated Project Plan • Project Master Schedule • Escalation Strategy • Work Breakdown Structure • Project Code of Accounts • Contracting Strategy Engineering Deliverables: • Block Flow Diagrams • Plot Plans • Process Flow Diagrams (PFDs) • Utility Flow Diagrams (UDFs) • Piping & Instrumentation Diagrams (P&IDs) • Heat & Material Balances • Hydraulic Calculation • Process Equipment List • Utility Equipment List • Electrical One-Line Diagrams • Engineering Specifications • Equipment Data Sheet • Gen. Equipment Arrangement Drawings • Spare Parts Listings © 2015 Yosep Asro Wain Conceptual Study (CS) Feasibility Study (FS) Basic Engineering Design (BED) Front End Engineering Design (FEED) Detail Engineering Design (DED) General Assumed General None None None None None None Assumed Preliminary Preliminary Approximate Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Assumed Defined Defined Specific Defined Defined Defined Defined Defined Defined Preliminary Defined Defined Specific Defined Defined Defined Defined Defined Defined Defined Defined Defined Specific Defined Defined Defined Defined Defined Defined Defined S/P P/C S/P P S/P S/P S/P S/P S/P S/P S/P S S S C C C C C C P/C C C C P/C P/C C P C C C C C C C C C C C C C P C C C C C C C C C C C C C C www.pmworldlibrary.net Page 7 of 11 PM World Journal Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Vol. IV, Issue V – May 2015 www.pmworldjournal.net Featured Paper Deliverables • • • • Conceptual Study (CS) Feasibility Study (FS) Basic Engineering Design (BED) S/P S/P S/P S/P Front End Engineering Design (FEED) P/C P/C P/C P/C Detail Engineering Design (DED) C C C C CLASS 5 CLASS 4 CLASS 3 CLASS 2 CLASS 1 Mechanical Discipline Drawings Electrical Discipline Drawings Instrument/Control Discipline Drawings Civil/Structural/Site Discipline Drawings Cost Estimation Yosep Asro Wain Note: S: Start; P: Preliminary; C: Completed Even though most of engineering deliverables have been completed in BED phase, however in the further phase, if necessary these documents may be updated. 3D-WBS in Engineering Design 5. As mentioned above, besides product in form of deliverable, engineering design activities also has another dimension, namely phase. Hence, it is prefer to combine the deliverable and the phase in a single form, instead of let them in separate form. Combining of the deliverable and phase of the engineering design works in one structure has advantages, including: • The whole activities are seen as a continuous process, starting from initial or conceptual phase until detail design phase. • Using a single format of document, including reporting. • More efficient and effective. Figure 7: 3D-WBS of Engineering Design For implementing of 3D-WBS in engineering design, one more dimension should be added, in this case is zone or location of the project. As each location has uniqueness, use the project location as one of the 3D-WBS side is the right thing. So that 3D-WBS of engineering works has deliverables as the PBS side, engineering phase as the ABS side and project location as ZBS side, as shown in figure 7. © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 8 of 11 PM World Journal Vol. IV, Issue V – May 2015 www.pmworldjournal.net Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Featured Paper Yosep Asro Wain As shown in Figure 8, ZBS has one level that is Project Area, PBS has two levels that are engineering deliverables, and ABS has one level that is Engineering Phase. Please noted that the level of each side may be extended if necessary. With reference to Table 1, PBS side consist of 3 groups of deliverables as level 1, that are General Project Data, Engineering Deliverables and Cost Estimation. While the level 2 of PBS containts detail deliverables of each group. Figure 8: 3D-WBS of Engineering Design in Matrix View 6. WBS Dictionary WBS Dictionary is a complement of the WBS. It provides the definition for each component contained in the WBS. Typical Content of WBS Dictionary is: - Description. - WBS Sructure. - Key Deliverables. - Key Activities. - Resources Composite. - Schedule. © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 9 of 11 PM World Journal Vol. IV, Issue V – May 2015 www.pmworldjournal.net 7. Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Featured Paper Yosep Asro Wain Summary WBS is a hierarchical decomposition of the scope of work, with the lowest element a work package, which can be scheduled, estimated, monitored and controlled. There are many breakdown structures i.e. product based work breakdown structure (PBS), activity based work breakdown structure (ABS), zone based work breakdown structure (ZBS), functional based work breakdown structure (FBS), etc. To mix these structures, it is developed 3-dimension of work breakdown structure (3D-WBS), which could be represented by one cube, with three sides. Using 3D-WBS for engineering design, which has product, phase and zone dimensions, has advantages, i.e.: 8. The whole activities are seen as a continuous process, starting from initial or conceptual phase until detail design phase. Using a single format of document, including reporting. More efficient and effective. References Humphreys, G.C. 2011. Project Management Using Earned Value, Chapter 2, page 45 to 58. Humphreys & Associates, Management Consultants. Second Edition. PMI. 2013. A Guide to The Project Management Body of Knowledge (PMBOK Guide), Fifth Edition, Chapter 5.4, page 125 to 132. PMI (Project Management Institute). US GAO. 2009. GAO-09-3SP, GAO Cost Estimating and Assessment Guide, Chapter 8, Page 65 to 78. US GAO (United States Government Accountability Office). Moine J-Y. 2013. 3D Work Breakdown Structure Method, PM Word Journal Vol. II, Issue IV – April 2013. Mody D and Strong DS. An Overview of Chemical Process Design Engineering, Queen’s University. Retrieved from http://library.queensu.ca/ojs/index.php/PCEEA/article/viewFile/3824/3876 AACE International. Recommended Practice No. 18R-97. (2011), Cost Estimate Classification System – As Applied in Engineering Procurement and Construction. © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 10 of 11 PM World Journal Vol. IV, Issue V – May 2015 www.pmworldjournal.net Implementation of 3-Dimensional Work Breakdown Structure in Engineering Design Featured Paper Yosep Asro Wain About the Author Yosep Asro Wain Jakarta, Indonesia Yosep Asro Wain is a professional in oil and gas, especially in refinery fields with 20 years experiences. The most of his job are in the project management field, namely project engineering design, project budgeting, project cost estimating, project cost control, project scheduling and contract engineering. He is currently a cost engineering specialist at Engineering Center, Refinery Directorate of Pertamina. Yosep holds a bachelor degree in Electrical Engineering (in Control Engineering field) from Bandung Institute of Technology (ITB), and is a Certified Cost Professional (CCP-AACEI). He is also a senior process control and instrumentation engineer. He lives in Jakarta, Indonesia and can be contacted at yosepasro@yahoo.com. © 2015 Yosep Asro Wain www.pmworldlibrary.net Page 11 of 11
© Copyright 2026